Most sites put fitters, electricians and controls engineers under one word: maintenance. They do different jobs. Send the wrong trade to a breakdown and the first hours go on finding out it is someone else's job. This post shows how to work out the mix your site needs, using your own fault log.
What each trade covers
A fitter owns the things that move. That means bearings, gearboxes, chains, belts, couplings, hydraulics, pneumatics and guarding. Fitters read wear. A good one can hear that a bearing is on its way out before it fails. On a site with old, heavy kit, most breakdowns land here.
An electrician owns the power and the wiring. That covers motors, starters, contactors, overloads, inverters, control circuits, sensors and the cables between them. On a modern line, a big share of stoppages are electrical. Many of them are small. A prox gets knocked out of line. A terminal works loose. A contactor coil fails. An inverter trips on an earth fault. These are quick fixes for the right person. For the wrong person they mean a long night.
A controls engineer owns the logic. That means PLCs, HMIs, servo set-up, networks and safety controllers. They can go online, watch the inputs change and tell you which signal never arrived. You may not need one every day. When you do, nobody else will do.
The trades overlap at the edges. A good electrician can go online and read a ladder. A good controls engineer can wire a panel. Still, each trade has a centre, and faults tend to sit in one of them.
Why sending whoever is on costs you
Sending the wrong trade does not usually make the fault worse. It makes it slower.
Take an inverter that has tripped on an earth fault from a chafed cable. A fitter will work through everything mechanical first, which is the right thing for a fitter to do. That can take an hour. Then comes the phone call, and the wait for someone who can deal with the drive. On a line that earns its keep by the hour, that is real money. Multiply it by the number of times it happens in a month.
There is also a safety point. HSE's guidance on the Electricity at Work Regulations says the operation, maintenance and testing of electrical systems "must only be carried out by those people who are competent for that work". Under regulation 16, anyone without the knowledge or experience has to be supervised. A fitter alone on nights with a drive fault is exactly who that rule is about. They may be keen to have a go. That is when someone opens a panel they should not.
Controls work has its own trap. A change to a PLC program, even a small one, can change what a safety function does. If it changes how the machine behaves, treat it as a modification, with all the duties that brings.
Let your fault log decide
You do not need a consultant to work out the mix. You need six months of breakdowns.
Go through your log and put each stoppage into one of four piles:
- mechanical
- electrical
- controls
- operator or process
Be honest with the last pile. Plenty of breakdowns turn out to be a product change or a jam. Then look at each pile in turn. Count how many faults land in it. Work out how long they took to fix, on average. Note what time of day they happened.
The count tells you where the volume is. The fix time tells you where the hours go. Often the electrical pile is bigger in count but shorter per fault. Mechanical faults may be fewer but longer. The time of day tells you who you need on which shift.
If your log cannot give you this, fix the log first.
What the answer usually looks like
Every site is different, so treat this as a starting point.
Older, heavy plant with few drives tends to need more fitters. A modern packing or logistics site with conveyors, sorters and servo kit tends to need more electricians. Sensors and drives are where those sites stop.
Few sites need a full-time controls engineer. Most need one they can get hold of when the logic goes wrong. They also need electricians who can at least go online to the PLC and look. Our post on the multi-skilled engineer covers how far one person can stretch.
Then cover the shifts. If most electrical faults happen on nights, your electrician should not be on days only. That sounds obvious. It is also how a lot of rotas are built, because days is what people asked for. See shift patterns for maintenance teams for the options.
Where you cannot justify a full-time trade, plan how you will get one when it is needed. Options include:
- a known engineer you can call
- an agreement with the machine builder
- temporary cover booked for the risky weeks
What you want to avoid is working it out at 2am.
Our view
Ask "which trade?" before you ask "who's free?". Build the team from your fault log. Put cover on the shift where the faults happen. Have a plan for any trade you do not hold. Sending the wrong person for two hours is one of the most common costs in maintenance. It is also one of the easiest to avoid.
Before the end of the week:
- Sort the last six months of breakdowns into the four piles.
- Check which shift each pile lands on. Compare it with who is on that shift.
- Write down who you call for a drive or PLC fault on nights. Put the number on the board.
Next step
If your fault log shows a gap in your maintenance team, send us a brief or book a call. If the brief will be hard to fill, we will tell you and help fix it.